National Highways Wing |
Projects |
IMPROVEMENT OF NATIONAL HIGHWAYS PROPOSED UNDER 2014-15 ANNUAL PLAN:- |
Annual Plan for various works on different NHs during 2014-05 has been finalized by GOI. The Plan Programme envisages improvement of NHs on the following fields. |
- Road Works Rs. 1310.72 Cr.
- Bridge works Rs 138.36 Cr
|
Programme |
Works Proposed for sanction under AP of 2014-15 |
Sanctioned under
AP of 2014-15 |
Length in km/Nos |
Amount ( Rs in Cr) |
Length in ( km/Nos) |
Amount ( Rs in Cr) |
Widening to two Lane |
298 |
1135 |
|
|
Strengthening ( Paved shoulder) |
0 |
0 |
|
|
Improvement of Riding quality |
0 |
0 |
|
|
Road safety ( identified projects) |
7 |
72 |
|
|
Pre-Construction activities for BY Passes |
6 |
102.50 |
|
|
Consultancy services for re-alignment and four laning |
36.22 |
1.22 |
|
|
Re-construction of Major bridges |
4 |
32.78 |
|
|
Re-construction of MBs |
43 |
73.00 |
|
|
Consultancy services/Rehabilitation |
|
32.58 |
|
|
|
IMPROVEMENT OF NH UNDER EXTRA BUDGETORY SUPPORT : |
Improvement 320 km length of single/ intermediate/Double lane NHs has been proposed for improvement to two lane with paved shoulder under NHIIP and NHDP. Present position of the works is given below. |
Sl.
No. |
Programme |
Old NH |
New NH |
Corridor |
Length in kms |
Estimated
Cost
Rs in Cr |
Present status |
1. |
NHIIP |
200 |
49
53 |
Bhojpur to Chhatabar |
61 |
185.48 |
RFP to be invited shortly |
2. |
NHIIP |
201 |
26 |
Nabrangpur to Koksara |
55 |
197.35 |
RFQ under finalization |
3. |
NHIIP |
217 |
353
59 |
Nuaparha to BangoMunda |
68 |
148.67 |
Work in progress. |
4 |
NHDP |
200 |
49 |
Kanaktora to Jharsuguda |
68 |
319.80 |
Work in progress. |
5 |
NHDP |
23 |
149 |
Palhara to Pitri |
68 |
342.05 |
Last date of submission of RFP is 04.09.14 |
|
|
|
|
Total |
320 |
1193.35 |
|
|
Provision of funds for improvement of NHs by State Government: |
As there is a wide gap between requirement and allocation of funds for “Maintenance and Repair” of NHs in Odisha, Government of Odisha has provided Rs 66.17 crore under “Special Repair head” during 2014-15 for improvement stretches annexed as Annexure-A |
Construction of BY pass and BY Pass cum ROB near congested towns/ Level crossing: - |
Proposal for construction of BY pass for the following towns has been proposed and Detailed Project Report has been finalized. |
- BY Pass near Koraput on NH 43
- By Pass near Borigumma on NH 201 & NH 43
- By Pass Jeypur on NH 43.
- BY Pass cum ROB near Berhampur on NH 217
- By Pass cum ROB near Bolangir on NH 201.
- By Pass cum ROB near Titilagarh on NH 217.
- BY Pass cum ROB near Belpahar on NH 200
- BY Pass near Nabarangpour on NH 201
- Construction of Belpahar By-Pass is in progress under EPC mode.
- Pre-construction activity for Berhampur and Bolangir by Pass are in progress.
- There is provision for sanction of “Pre-construction activity” estimate for Koraput, Jeypore, Borigumma, Nabarangpur and Titilagarh By-Pass under AP of 2014-15
|
|
|
|