Also there is proposal to improvement of 557.485 km comprising 354.604 km of Single lane, 112.558 km of Intermediate lane and 90.323 km two lane under Special Project under World Bank assistance for which Ministry of Surface Transport Highways, G.O.I has engaged consultant for preparation of D.P.R. |
|
Sl.No |
NH |
Corridor |
Stretch |
Length in km |
Present position |
From |
To |
1. |
23 |
Pallhara-Pitri-Junction |
337.47 |
405.48 |
68.01 |
Consultant has been engaged by GOI for preparation of DPR |
2. |
217 |
Belgaon-Baliguda |
202.89 |
319 |
116.11 |
3. |
200 |
Rengali-Talcher |
227 |
295 |
68.00 |
4. |
217 |
Daringibadi-Sorada |
375 |
439.365 |
64.365 |
5. |
224 |
Daspalla-Madhapur |
102 |
159 |
57.0 |
6. |
200 |
Bhojpur-Chhatabar |
131 |
192 |
61.0 |
7. |
201 |
Nawarangpur-Koksara |
25 |
80 |
55.0 |
8. |
217 |
Nuapada-Bangamunda |
90 |
158 |
68.0 |
|
|
Total |
|
|
557.485 |
|
Position of V-R Highways in Odisha |
239.3 of NHs are coming under NH network. Out of which 31.5 km is coming under NHDP phase-III which is under implementation by NHAI. Present status of NH coming under V-R Highway section is given below. |
|
Total length of NH under V-R Highway |
Length to be transferred to NHAI |
Balance length with NH wing (1-2) |
Length improved |
Two Lane under Progress |
To be improved |
Length improvedPreviously |
Length recently improved |
Total |
239.3 |
31.5 |
207.8 |
144.00 |
4.8 |
148.8 |
57.00 |
2.00 |
There is provision in Annual Plan of 2010-11 for improvement of the remaining stretch of 2 km to TwoLane. |
|
|
|